Ceramic factory "Komstroy", Russia
Project description
Stage 1: development of a system for automated control of a brick production technology line - developed microprocessor controller, electronic apparatus, full start.
Stage 2: reconstruction and modernization of a second technological line for the introduction of automated handling of the loading-unloading and packing process.
Project brief
| Year of realization | 2007-2008 (Stage 1) 2013-2014 (Stage 2) |
| Customer | OOO "KomStroy" |
| Location | RF, Rostov region, Sakhty |
Project results
Stage 1: delivered in operation according to design indicators 30 million pieces of conventional single bricks.
Stage 2: the second section of a brick production line was put into operation in 2014 on planned design indicators.